CLIENT
Div IV, Electricity Department, Govt. of Goa, Margao, Goa
Started on
23 February 2001
Completed on
12 October 2002
Supply, Erection, Testing & Commissioning of 33 KV D/C line from Verna to Pajifond, Margao via Fatorda (16.5 km length)
Nature of Work
Surveying, Supply, Erection, Testing & Commissioning of 33 KV D/C line 16.5 Km including Erection of 4 pole structures, 9 pole structures, 3 pole structures, 2 pole structures; G.O.A.B switches etc;