CLIENT
Prakash Corrugated Packaging Products, Verna
Started on
17 September 2013
Completed on
7 March 2014
Work of Supply, Erection, Testing and commissioning of 11/0.433 KV, 3 phase, 50 Hz, 250 KVA Transformer Substation and associated HT lines and Equipments for releasing power supply to M/s Prakash Corrugated Packaging Products, Verna Industrial Estate
Nature of Work
Work of Supply, Erection, Testing and Commissioning if 11/0.433 KV, 3 phase, 50 Hz, 250 KVA Transformer Substation and associated HT lines and equipments for releasing Power Supply to M/s Prakash Corrugated Packaging Products, Verna Industrial Estate